Several requests for the installation of EV chargers have followed one another within this 87-unit complex. In response to this movement, the condo board decided to put together an installation group.

Charging Solution

Since the technical context allowed it, the Electric Vehicle Energy Management System (EVEMS) was designated as the charging solution

Installation Approach

The Condo Board chose to deploy the installations through an Individual Approach. 

Set Up

In December 2018, a Charging Policy was set up to facilitate and standardize the procedures. Then, in January 2019, the board contacted the tenants to organize the installation group. At the same time, the contractor submitted pricing.

Installation

A NEMA outlet as well as three car chargers were installed in January 2019.

Project Details

Work in the Electrical Room

Installation of 4 EVEMS

Work in the Garage

Installation of the piping and cabling for 3 chargers and one NEMA outlet

Work in the Parking Spaces

Installation of 3 chargers (Audi e-tron, Tesla Wall Connector and Flo G5) and one bare NEMA outlet

Rebate

This project took advantage of the Roulez Vert program established by the Quebec Government, specifically the “Borne de recharge en multilogement” section.

Location

Montreal, Quebec

Electrical Contractor